PHASE 1

  • Start Design: 2013, Online: 2018
  • 2020 Demand: 5,000 acft/yr
  • Capacity: 15,000 acft/yr
  • GW WTP Capacity: 27 MGD
  • Supply: Groundwater Only
  • SW Pipeline to ASR WTP: none
  • FW Pipeline to DP1: 42", 36", 30"
  • FW Pipeline to DP2: 20"
  • Carrizo: 13 production wells
  • ASR Well Field: none

PHASE 2

  • Start Design: 2025, Online: 2030
  • 2030 Demand: 15,000 acft/yr
  • Capacity: 25,000 acft/yr
  • ASR WTP Capacity: 45 MGD
  • Supply: GW, SW, ASR
  • SW PL to ASR WTP: 54"
  • SW Intake and PS: 45 MGD
  • FW PL ASR WTP to Luling PS: 36

PHASE 3

  • Start Design: 2035, Online: 2040
  • 2040 Demand: 25,000 acft/yr
  • Capacity: 32,000 acft/yr
  • FW Pipeline to DP1 (P2): 48"
  • FW Pipeline to DP2 (P2): 36"

PHASE 4

  • Start Design: 2045, Online: 2050
  • 2050 Demand: 32,000 acft/yr
  • Capacity: 37,000 acft/yr
  • FW PL ASR WTP to Luling PS (P2): 54"

PHASE 5

  • Start Design: 2055, Online: 2060
  • 2060 Demand: 42,000 acft/yr
  • Capacity: 42,000 acft/yr
  • ASR WTP Capacity: 63 MGD
  • SW Intake and PS: 63 MGD
  • ASR Well Field: 30 ASR Wells

Mid-Basin Water Supply Project

Phase-by-phase

Feature Info